Mining Operation

drp-200-1

PT. DIRAR DUAGE ENERGI (DDE)

PT. DDE coal consession has started production by the end of year 2013.

Right now, there is only one pit at block A (map attached).

Production capacity at block A DDE is 30.000 MT/month.

drp

PT. DIANRANA PETROJASA (DRP)

PT. DRP coal consession has started production in mid year 2010.

Right now, there are three blocks operating, i.e block 2, block 3 and block 4 (map attached).

Production capacity is 15.000 MT/block/month.

tmp-200

PT. TRI MANDIRI PERKASA (TMP)

PT. TMP coal consession has started production by the end of year 2012.

Right now, there is only one block operating, i.e block 1 and will be operating soon one more block by the end of year 2014. (map attached).

Production capacity at block 1 is 30.000 MT/month.

cbr-200

PT.CITRA BARA RAYA (CBR)

PT. CBR coal consession has started production by the end of year 2014.

Production capacity CBR is 10.000 MT/month.

cbr-200

PT.KASIH KARYA AGUNG (KKA)

PT. KKA coal consession has started production by the April 2015.

Production capacity KKA is 15.000 MT/month.